Challenge

When LinkedIn purchased this existing concrete tilt-up commercial building in Sunnyvale they wanted to do something special with their renovation. California has a building code requirement coming in 2030 that all commercial buildings will have Zero Net Energy (ZNE) use. LinkedIn made the forward step to upgrade this building to ZNE well ahead of the upcoming California requirement. This renovation required that all systems be of the highest possible efficiency, including the roof.

Solution

CCC installed a four-inch-thick SPF roof which provided R-25 of continuous insulation for this commercial building in Silicon Valley. However, with no gaps and no fasteners, the monolithic SPF roof provides higher performance insulation than rigid insulation board systems. This fully adhered SPF system also allowed the exposed wood ceilings to be free of unsightly fasteners being visible through the roof like when rigid insulation systems are installed.

This project also included careful design considerations needed to incorporate the new foam roof with the commercial roof HVAC, photo-voltaic system and dozens of new skylights for increased “daylighting.”

Project Overview

The Bee Sweet processing plant includes several conjoined metal buildings, with a combined square footage over 250,000 square feet. Bee Sweet wanted improved waterproofing, a common issue when metal buildings are conjoined. They opted to add 88,600 sf of spray polyurethane foam (SPF) roofing to an existing 133,720 sf SPF roof. To maximize energy efficiency, they concurrently replaced and sealed 54 skylights, and added a 2.4-megawatt photovoltaic (PV) system with over 7,400 solar panels requiring 7,487 standoffs, each penetrating the roof and requiring a leak-resistant seal.

Challenge

Environmental stewardship is one of Bee Sweet’s corporate priorities. Their commitment to be as environmentally friendly as possible in every step of the growing, picking and packing process drove the decision to upgrade their processing plant to conserve electricity and minimize their environmental footprint. This complicated project included SPF roofing, skylight replacement, and installation of a large rooftop PV system. Although the existing SPF roof was already in place, more roofing was needed when the decision was made to add the solar panels. Bee Sweet selected a 2.4-megawatt PV system that covered almost the entire plant, including the existing foam roofs and citrus processing area.

The 88,600 sf processing area had experienced many leaks and  needed additional insulation, so a new foam roof was added prior to PV system installation. The massive PV system required a staggering 7,497 standoff brackets fastened into the roof as structure.  More than one-third of these brackets were sealed as the new SPF roof system was installed. The remaining brackets had to be installed and sealed in the existing foam roof area. Additionally, the processing area had 54 fiberglass skylight panels that were failing. SPF contractor Central Coating Company removed these panels and installed and sealed 54 new curb-mounted, double-lens skylights to improving lighting and increase safety. Despite the size and scope of this project, all work had to be performed without disrupting daily business operations.

Challenge

This existing standing seam metal roof had been the source of past roof leaks. In addition, this building was due to receive a daylighting upgrade to match the other campus buildings which use hundreds of Sun Tube skylights to provide natural light to the work spaces.

Solution

CCC installed a new sprayed foam roof to waterproof and insulate the existing metal roof. During the project several dozen new Sun Tube skylights were installed which bring daylight into the work spaces below.

Challenge

The existing tar and gravel roofs on the hotel had been a source of leaks for many years. After researching many different roofing systems, the ownership found that a foam roof by CCC would provide the best solution at the best price with the least impact on the hotel. The project was complicated by the roof being separated into many different section on several different levels. Also, noise and disruption were a big issue as the hotel lodges flight crews arriving from Asia into SFO airport.

Solution

CCC removed the surface gravel and prepare the existing roof to receive SPF roofing. CCC also had to perform an extensive amount of detailed preparation work around HVAC units, electrical panels and cell phone equipment. This difficult project required daily coordination with the hotel staff as the flight crews arriving from Asia had to be placed in rooms that would not be disturbed by that day’s roofing activities.

Challenge

The SPF roof on Paramit’s building was originally installed when the building was constructed. The foam roof was performing well and had at least five years of life remaining before a recoat would be required. However, Paramit wanted to install a roof top PV system which would cover the entire roof top. The ownership made the decision to have CCC recoat the roof to match the lifespan of the roof with the lifespan of the solar panels.

Solution

CCC cleaned and pressure washed the surface of the existing roof. The roof was then recoated with a high tensile strength acrylic coating and a fresh application on granules. The roof was warranted with a 15-year manufacturer’s warranty. After recoating, it is expected that the foam roof will provide another 25 years of performance which is the same as the performance expectation of the solar installation.

Challenge

The existing 1960’s era classroom and administration buildings were in need of a new roof and the lack of existing insulation led to classrooms which were nearly impossible to heat and cool to a comfortable level. Beyond providing a roofing and insulation solution, the new roof needed to maintain the aesthetic of the existing volcanic rock roofs while meeting the CalGreen Code requirement needed in Palo Alto.

Solution

CCC installed a Spray Foam roof providing R-30 insulation. Instead of the standard white topcoat and granules, CCC installed a custom color, “Spicy Hue” to match the existing aesthetic.

Challenge

The reroofing of this building followed the change of use of half the building from labs to office. On the remaining office side, a large amount of mechanical and process equipment was present requiring careful detailing of the roof. On the office side hundreds of abandoned sleepers, curbs and penetrations were present.

Solution

CCC installed a new SPF roof system which provided roof insulation, increasing the building’s thermal insulation by over 40%. During the project CCC’s crew demolished all of the abandoned sleepers and equipment platforms requiring 3 crane lifts to remove all of the debris.

Challenge

The reroofing of this Google building proved to be a challenge due to the presence of a large amount of HVAC and process piping as well as over 400 solar panels.

Solution

Google turned to CCC for the roofing solution. By using the sprayed in place roof system, CCC was able to provide a long lasting roof system without removing any equipment or affecting the production of the photovoltaic system.

Challenge

Columbus Salami occupied this building as a distribution center. In 2011, Columbus moved their salami slicing and packaging operation into the facility. Columbus looked to CCC to install a new foam roof to insulate and protect this food processing facility.

Solution

CCC installed a new SPF roof system working with the general contractor to seal the many complicated penetrations for cooling equipment.

Challenge

During the renovation of this building, Google replaced all interiors, mechanical equipment and the roof. Google turned to CCC to provide an insulated roofing solution as part of this fast track renovation project.

Solution

CCC installed a new foam roof in a phased approach, allowing the old rooftop equipment to be removed and new equipment installed while maintaining a watertight roof in the rainy season.

This project received the Spray Polyurethane Foam Alliance (SPFA) National Industry Excellence Award in 2005.

Challenge

Install a photovoltaic (PV) solar panel system on roof of a building where an engineer had determined that the roof”s loading capacity was at its limit and no additional weight could be added.

Solution

The existing built up roof (BUR) was torn off and replaced with a light weight SPF roof system resulting in roof loading reduction of approximately 120,000 lbs. The resulting reduction in roof load allowed for installation of a 267 kW PV system.

Download SmartStand Profile

Download SmartStand Brochure

Challenge

This refrigerated storage and logistics warehouse was experiencing high energy bills and had difficulty maintaining temperature on hot days in the San Joaquin Valley. At the same time the existing built up roof had reached the end of its useful life causing water and vapor leaks.

Solution

CCC installed a new sprayed polyurethane foam roof system with a vapor barrier coating. This stopped the leaks and increased the roof insulation providing substantial energy savings.

Challenge

Provide a Title 24 compliant roof system as part of a project to convert older existing buildings into a 21st century home for one of the country’s leading high tech companies.

Solution

Tear off BUR capsheet roof system. Apply one inch of SPF to plywood decking followed by bright white high-performance “Cool Roof” coating system.

This project received the Spray Polyurethane Foam Alliance (SPFA) National Industry Excellence Award in 2007.

Challenge

  1. Complete project during short summer vacation period.
  2. Gymnasium ceiling was left exposed requiring that no mechanical fasteners could penetrate the roof deck and be visible from below.
  3. Several lower roof levels were constructed “dead flat” requiring that slope to drain be achieved with CCC’s SpraySlope™ slope to drain SPF roof system

Solution

  1. All foaming completed before school started and coating application phased around first days of school year.
  2. Insulation requirement for project was R-22. To achieve this, high-density polyisocyanurate boardstock was secured to the top of the fluted metal deck using Dow Chemical Insta-Stick Adhesive instead of mechanical fasteners. Then two 1 inch passes of SPF were installed over the boardstock.
  3. On the “dead flat” roof areas tapered passes of SPF were installed to form slope to drain at ¼ inch per foot. At its thickest point the SPF is 8 inches thick. CCC provided the insulation, slope to drain system and roof membrane within its scope of work. Having three separate scopes of work performed by one trade saved time and money for the client.

Challenge

Waterproof a large building in an area with high winds and provide an energy efficient “Cool Roof” coating system on a rapid schedule to meet general contractor’s schedule

Solution

CCC mobilized two crews, two foam rigs, and a dedicated rigid insulation board installation crew. In open areas of the roof CCC was able to install the rigid insulation board and sprayed polyurethane foam at a rate of 20,000 sq. ft. per day. The project was finished ahead of schedule.

The roof system had to be installed to meet Factory Mutual’s 1-90 Wind Uplift Rating due to the high winds common in the Ontario Area. SPF roofs offer the best wind uplift performance of any commercial roof system.

The roof system provides R30 insulation over the showroom and office and R19 insulation over the warehouse. SPF roof system was coated with bright white highly reflective coating to meet “Cool Roof” requirements.

Quote from the General Contractor:
“Central Coating’s on-site crew size was more than adequate to perform the task at hand and was able to adjust to varying conditions seamlessly. You have my recommendation without reservation.”
-Tony Ageno, Project Superintendent, Devcon Construction.

Challenge

Provide a high performance insulating roof system for a highly leak sensitive client on a building with literally hundreds of roof deck penetrations.

Solution

Install (3) one inch thick passes of SPF over a properly prepared and primed concrete deck. The unique self-flashing capabilities of SPF were utilized to form cones and cants around hundreds of roof penetrations. High performance GE Silicone coating system and 3M ceramic granules were installed to protect the foam from UV radiation and roof traffic. This roof was designed to protect this building and its contents for the life of the building.

Challenge

Re-roof all 17 buildings of a large apartment complex as one project. The owner was fed up with the persistent roof leaks. CCC was hired to do the job right.

Solution

CCC followed a phased approach completing 4 buildings from each set up location. The roof added R-9 of insulation and upgraded the buildings with Cool Roof technology. Due to the shape of the buildings the preparation and sheet metal details were very complicated. CCC replaced over one and a half miles of edge flashing and 198 scuppers with new downspouts. The project was completed on schedule and will provide decades of leak free performance.

Challenge

Replace an aging tar and gravel style built up roof without disrupting the operations of a high-tech client. In addition to the roof leaks, the large amount of duct work present on the roof was also the source of water leaks and air leaks. The large HVAC system including several hundred linear feet of chilled water supply & return piping made for a challenging installation.

Solution

Preparing this roof for foaming involved removing the surface gravel using a high powered wet vacuum. This provided an excellent substrate for the new roof without the expense and inconvenience of a tear-off. CCC installed 1-1/2 inches of SPF over the roof and also foamed several thousand square feet of ductwork. The duct foaming provides a huge increase in energy efficiency by stopping air leaks and adding insulation to the ducts. CCC used its proven flashing and preparation techniques around the HVAC units and piping. On this project CCC once again proved its ability to provide a high quality roof on an occupied facility.

Challenge

When Plantronics decided to go solar they turned to CCC as their roofing partner. In addition to a new insulated roof and photovoltaic power generation, Plantronics wanted to improve the lighting efficiency of the building with the use of sun-tube skylights.

Solution

CCC installed its SmartStand™ solar racking which provides an integrated roofing and solar racking solution. CCC also sealed over 120 sun-tube skylight roof penetrations which eliminated the need for lighting throughout most of the building.

Challenge

Client wanted to eliminate roof leaks and take advantage of Sacramento Municipal Utility District (SMUD)’s cool roof energy rebate program. Client had multiple buildings in a campus setting.

Solution

In phase I CCC replaced leaking skylights which were not CAL-OSHA compliant, filled deflected areas where ponding water existed and installed a new energy efficient “Cool Roof” roofing system with bright white reflective coating and granules. Client received a $0.20/sq. ft. rebate from SMUD, Phase I was so successful that CCC was brought back to do three additional office buildings.

Challenge

The existing asphalt roof had failed as a waterproof membrane and as a vapor barrier. Maintenance costs were escalating and valuable electricity was being wasted.

Solution

After the SPF roof and vapor barrier coating system was installed, the frost and ice inside the building has dissipated (evaporated). A review of electricity bills from before and after installing the SPF roof and vapor barrier on the Union City project showed a savings of $8,000 per month. The entire cost of the project will be recovered in approximately seven years.

Challenge

Central Coating’s first ElectroRoof® project, designed to demonstrate the synergy of integrating an SPF roof to save energy and a photovoltaic (PV) panel installation to generate electrical energy.

Solution

Stanchions to support the PV panels were installed on a new plywood deck and permanently sealed as the new SPF roof was installed. The PV installation not only generates electricity, it is a research facility. The performance of several photovoltaic arrays of different panel types, and panel tilt angles can be monitored separately.

Challenge

Working on a super fast track schedule to provide the roof on a building that is literally covered with equipment and thousands of roof penetrations.

Solution

SPF roof, due to its fluid nature, easily conforms to the shape of various roof penetrations providing a water tight seal. Central Coating Company worked with the general contractor to meet or exceed all schedule requirements.

Challenge

Client constructed new warehouse for olive can storage and needed a leak free storage facility.

Solution

CCC was brought in by Food Pro International to install a 100% seamless SPF roof system. Due to the success of this project we were invited back to complete Phase II and III of Musco’s plant expansion as well as roofing the office building and processing area.

Challenge

Re-roof 70,000 square foot building in one weekend.

Solution

Bring in four foam trailers and 22 men to meet client’s schedule

Challenge

The Pier 70 project presented several challenges that made a sprayed polyurethane foam (SPF) roof the perfect solution for this hundred-year-old facility. Because of its designation as a historical building, there was no requirement for thermal roof insulation which meant that the radiant heat from the metal roof created an uncomfortably warm interior for occupants. In fact, infrared imagery documented internal heat temperatures as high as 135° on warm days on the underside of the metal roof, causing ambient temperatures that exceeded 85° in this high-tech, un-conditioned office space.

Solution

A two-inch thick layer of spray foam was chosen as the only viable solution to the radiant heat issue when also considering the strict historical society standards. This resulted in an underdeck temperature reduction of as much as 40° on warm days and considerably increased comfort for employees. So, the spray foam roof stopped recurring leaks, added seamless and continuous insulation, and maintained the building’s historic status.

Challenge

This biotech laboratory project presented a major challenge for our coating restoration team. With a complex maze of mechanical units, piping, and other equipment that had to be avoided, the project was a major logistical challenge. The installation process required careful planning and precise execution to ensure that the coating was applied correctly without damaging any of the sensitive equipment. The project was further complicated by a tight schedule, which left very little room for error.

Solution

Despite the numerous obstacles we faced, our team was able to complete the project successfully. We started by conducting a thorough survey of the laboratory roof to identify all the areas that required coating restoration. We then created a detailed plan of action that incorporated strategies for working around the equipment and piping. The team also made use of specialized equipment and tactics to access the hard-to-reach areas. We coordinated closely with the laboratory staff to minimize disruptions to their ongoing research activities. With careful planning and precise execution, we were able to complete this coating restoration project on time and to the satisfaction of the client.

Challenge

Installing a spray polyurethane roof (SPF) on a luxury apartment complex in Mt. View, California presented several unique challenges. Despite the relatively small total area of the roof, the square footage was spread across dozens of smaller roofs, making it a challenging installation. The project also required the installation of almost a mile of new edge metal flashing along all sides of the multiple roof areas, adding to the complexity of the installation. Finally, the existing roof structure had exposed wood sleepers that needed to be covered with new metal sleeper caps before the SPF could be applied.

Solution

Despite the challenges we faced, our team was able to successfully install the SPF roofing system on the luxury apartment complex. We started by creating a detailed plan that took into account the unique challenges of the project, including the need for new edge metal flashing and metal sleeper caps. We worked closely with the building owners to ensure that the project was completed on time and within budget. Our team had the necessary equipment, knowledge, and skills to ensure that the SPF was applied correctly and adhered properly to the surface. The result was a seamless and energy-efficient SPF roofing system that not only added insulation and comfort to the building, but also came with a 20-year warranty, providing peace of mind to the building owners and tenants alike.

Challenge

Central Coating’s spray foam roofing system was chosen for what is essentially the world’s largest battery, located in Moss Landing, California after other re-roofing solutions were considered and rejected. One of the main challenges of this project was the presence of an old tar and gravel roof that contained asbestos. This meant that other roofing solutions would require asbestos abatement to take place before a new roof could be installed, leading to added costs, time, and disruption to the building’s staff and possible exposure to the elements for the highly sensitive equipment inside. In addition, the need for a seamless roofing system that could withstand the local weather conditions presented additional challenges.

Solution

In the end, Central Coating’s spray foam roofing system was the perfect solution. Once any loose gravel was removed, our spray foam roofing system was installed directly over the existing roof, eliminating the need for asbestos abatement, and greatly reducing project costs and time. Our roofing system was also installed as a seamless roof over the entire facility, ensuring that it could withstand even the worst local weather conditions. The end result was a seamless, energy-efficient, and cost-effective roofing system that provided the world’s largest battery with superior protection against the elements.

Challenge

Central Coating was recently tasked with installing a spray polyurethane roof for Intermolecular, Inc. The client’s roof spanned an impressive 160,000 square feet, which contained several open areas. However, the biggest challenge was a 40,000 square foot section over a clean room. The clean room had a large amount of equipment that needed to be accommodated on the roof to ensure proper ventilation and filtration. This created a complicated installation process that required a high degree of skill and precision from Central Coating’s team.

Solution

To solve the challenge, Central Coating’s team worked closely with Intermolecular, Inc. to develop a unique installation strategy. They installed the spray polyurethane roof in sections, working around the complex equipment in the clean room. The team used their expertise to carefully navigate around the equipment to create a durable and energy-efficient roof. The installed roof also provided insulation which increased the comfort level for those working in the clean room and the rest of the building. So, despite the challenges posed by the clean room’s dense roof equipment, Central Coating was able to deliver a high-quality and long-lasting roofing solution for Intermolecular, Inc., thanks to our experienced team and innovative approach to problem-solving.